Chapter 3 Basic Operations
Performing Manual Operations
ATL P1000 Series User’s Guide 51
Performing Manual Operations
3
This section describes procedures requiring operator intervention.
These procedures consist of:
turning the library on
placing the library on-line
placing the library off-line
turning the library off
inserting tape cartridges
opening the library doors
manually ejecting a tape cartridge
Turning On the Library
3
To turn on the library:
Procedure
1
Verify that:
all internal packaging is removed
the front doors and load port are closed
the library enclosure is installed
all back panel connections are secure
2
At the front panel, set the AC power switch on.
3
After several seconds, verify that the GUI comes on.
Placing the Library
On-line
3
To place the library on-line:
Note:
You must have Operator level access privileges or higher to perform
this procedure (see “Changing the GUI Security Level” on page 49).
Procedure
1
With the library turned on and the GUI indicating “System Off-
line,” press the Standby button on the GUI.
2
Verify that the GUI displays “System On-line.”